Orascom Telecom CO. Iraquna Project

Orascom Telecom CO. Iraquna Project Iraquna Project Client: Orascom Telecom CO. Iraquna Location: Baghdad-Iraq Cost: 937,422.00 USD Duration: 2004- 2006 Iraquna is the Iraqi branch of Orascom Telecom CO. Iraquna contracted with CBuilding to design and construct multiple projects throughout Baghdad. Civil Projects: CBuilding constructed many buildings for Iraquna, Including: Service Buildings for the communication … Read more

Anbar Railway Stations

Anbar Railway Stations Client: KBR – (AL- ANBAR Province)Location: Anbar-IraqCost: 500,000.00 USDDuration: 370 DaysIn 2005 CBuilding was contracted to supervise and renovate all (30) railway stations in the sprawling Anbar. The detailed design followed.Cbuilding submitted all contract documents and followed up with the construction with intensive supervision and documentation.In all-around 60 engineers were involved with the project; work was being done simultaneously all around the province. The operation took around a year to finish and by the end all stations were ready to receive the trains.

Water Supply Baghdad Water Reservoirs Study

Water Supply Baghdad Water Reservoirs Study Client: ParsonsLocation: Baghdad-IraqCost: 370,000.00 USD Duration: 8 months In 2005 CBuilding was contracted to make replacements on Baghdad’s reservoirs, water treatment plants and pumping stations with attention to the flow meters.The contract was to replace the flow meters in the reservoirs that was responsible for measuring the flow rate and pressure of water in different pipes in the reservoirs.The company didin’t find a single flow meter in working condition, although several types and manufacturers were used.The reservoirs and pumping stations, however, were in working order and the valves were regularly maintained.

Schools Design , AGN, Assessment And Supervision.

Schools Design , AGN, Assessment And Supervision. Client: (AL- ANBAR Province) and Ministry of  EducationLocation: Anbar-IraqCost: 800,000.00 USD Duration: 2004-2006 During the last three years, Cbuilding has been involved heavily in the educational process.In 2004 Cbuilding carried out most of the design and supervision work to rehabilitate the schools in all of the Anbar province.This … Read more

(Autoclave and Shredding ) equipments in the Iraqi hospitals

(Autoclave and Shredding ) equipments in the Iraqi hospitals Client: CISALocation: Baghdad-IraqCost: 160,000.00 USD Duration: 6 months CISA Italian company signed a contract with the Iraqi Ministry of Health to work on the manufacturing, processing, and installation of (Autoclave and Shredding) equipment in the Iraqi hospitals, The company is currently implementing the first phase of … Read more

Al-Zaora Park Rehabilitation

Al-Zaora Park Rehabilitation Client: Al-Zaora ParkLocation: Baghdad-IraqCost: 450,000.00 USDDuration: 12 monthsIn 2005, CBuilding was awarded a contract for the rehabilitation of Al- Zaora Park pins. Work included many pins, with special requirements for some of the pins that house dangerous animals. Work included demolishing some of the old buildings and pins that were outdated, and meeting the … Read more

Guest house – Baghdad, Al-Mansour District. 2000

icon

Guest house – Baghdad, Al-Mansour District. 2000 (Design and Consultation) Client: the Arabian Company for Chemical productsLocation: Baghdad-IraqCost: 450,000.00 USDDuration: 15 months This project was built to be used by the clients of the Arabian Company for Chemical products.

Alamiriyah Hospital

icon

Alamiriyah Hospital  Design and Consultation The Amiriyah maternity is a 50-bed hospital. As well as inpatient care, it also has an outpatient facility, the emergency department, two operating theatres, four delivery rooms, and two IC units.  Also, it has a special ward for premature babies. The building occupies 3000m2 over two stories. It is provided with … Read more

Rehabilitation of the tourist city – Habbaniyah

icon

Rehabilitation of the tourist city – Habbaniyah Client: The Ministry of Tourism and AntiquitiesLocation: Baghdad-IraqCost: 400,000.00 USDDuration: 125 Days Our company has developed a tourist city – Habbaniyah. The implementation of sports fields and the development of the beach from the Tent restaurant to the (rock tooth) and supply, installation and operation of the beach’s … Read more

Private Luxury residential villas

Private Luxury residential villas turnkey basis including all engineering designs Client: Private residencies for clients in BaghdadLocation: Baghdad-IraqCost: 1,850,000.00 USDDuration: 1999-2004 They are about 50 villas and two four-story buildings of areas ranging from 300 m2 to 1200m2 and was constructed at the beginning of our company establishment at period from 1999-2004 for client from … Read more