PLC and SCADA Upgrading

Project: PLC and SCADA Upgrading for Haditha Diesel Power Station

Location: Haditha, Al-Anbar, Iraq

Starting date: June 13, 2022

Contractor: Al BINAA Al MOUASER

Duration: 27 Months

Completion: 80%

The control works in the project primarily focused on a comprehensive upgrade of the control systems at the plant. This includes the Programmable Logic Controller (PLC) and the Supervisory Control and Data Acquisition (SCADA) systems.